We Have Published "Japan Data Center Investment Trends: October 2026 Report"

Two Sheep Co., Ltd. has compiled recent data center investment activity in Japan from public information (as of October 28, 2026). The report covers press reports on talks between NTT DATA and Anthropic, NTT's plan to reach about 1 GW in Japan, large projects in Akita, Kagoshima and Hokkaido, the reuse of a former factory site in Sakai, the government's public-private investment roadmap, and the outlook for electricity demand.
Two Sheep Co., Ltd. has published "Japan Data Center Investment Trends: October 2026 Report", a summary of recent data center investment in Japan. It was compiled independently by Two Sheep from public information such as company and local government press releases, government documents and news reports (as of October 28, 2026). Items that come only from news reports are marked as such.
Key Points
- Reported (Nikkei, Oct. 13, 2026): NTT DATA Group is in final talks to build Anthropic's first dedicated data center in Japan, up to 500 MW (power-receiving) and up to about ¥1 trillion to build. Not officially announced
- NTT announced a plan to expand its domestic data center IT power capacity from about 300 MW to about 1 GW (more than three times) toward FY2033 (April 27, 2026)
- Regional plans: Satsumasendai, Kagoshima, 350 MW cumulative (city plan); northern Akita City, up to 500 MW power-receiving (reported). In Sept. 2026, 9 regions (10 sites) became data-center GX Strategic Areas
- The government's public-private investment roadmap (decided July 21, 2026) assumes ¥32.7 trillion of public and private investment through FY2035 for the "cloud and data centers, and batteries" item
- OCCTO, Japan's grid organization, forecasts peak demand of 6.61 GW from new and expanded data centers in FY2035. Securing power and grid-connection time are challenges for many of these projects
1. Press Reports: NTT DATA and Anthropic in Data Center Talks
On October 13, 2026, Nikkei reported that NTT DATA Group is in final-stage talks to build a dedicated data center in Osaka Prefecture for the US AI company Anthropic, which would be Anthropic's first in Japan. Reuters and others relayed the Nikkei report. The main points reported are:
- Location: the southern bay area of Osaka Prefecture is the candidate area (no specific site has been disclosed)
- Scale: up to 500 MW of power-receiving capacity and a construction cost of up to about ¥1 trillion. Including GPU servers, the total could reportedly reach several trillion yen
- Timing: the companies aim to sign by the end of FY2026 (March 31, 2027), with partial operation possibly starting as early as 2028
- Power: because drawing 500 MW from the grid takes time, alternatives such as on-site generation and fuel cells will reportedly be studied first (Nikkei Asia)
NTT declined to comment to Reuters. As of October 28, 2026, neither the NTT group companies nor Anthropic had made an official announcement on the matter. All of the reported figures are at the negotiation stage. Anthropic announced on October 29, 2025 that it had opened an office in Tokyo, its first in the Asia-Pacific region.
Overseas IT companies have also announced investments in cloud and AI infrastructure in Japan. On April 3, 2026, Microsoft announced it will invest US$10 billion (about ¥1.6 trillion) in Japan from 2026 through 2029, covering AI infrastructure, cybersecurity and workforce training. AWS announced on January 19, 2024 a plan to invest ¥2.26 trillion by 2027 in its existing cloud infrastructure in Tokyo and Osaka, and Oracle announced on April 18, 2024 a plan to invest more than US$8 billion over the next 10 years.
2. NTT: Domestic IT Power Capacity to About 1 GW
On April 27, 2026, NTT, NTT DATA Group and NTT DOCOMO BUSINESS announced that, alongside the rollout of the AI-native infrastructure "AIOWN", NTT plans to expand the IT power capacity of its data centers in Japan from about 300 MW today to about 1 GW, more than three times, toward FY2033. The main plans in that announcement (Chiba, Tochigi and Tokyo), plus separate announcements in Kansai and Kyushu, are:
- Inzai and Shiroi, Chiba Prefecture: a data center campus built in phases, eventually expanding to a total of about 250 MW of IT power capacity across the area
- Tochigi Prefecture: the Tochigi TCG11 Data Center at the Tochigi Inter industrial park, planned for completion in 2029 and eventually expanding to about 100 MW of IT power capacity
- Central Tokyo: NTT DOCOMO BUSINESS has started building an AI data center with liquid cooling as standard, about a five-minute walk from a station on the JR Yamanote Line, with service planned to start in the second half of FY2029
- Kansai and Kyushu: on April 9, 2026, NTT DATA opened the Keihanna OSK11 Data Center, with 30 MW of IT capacity, in the Keihanna area of Kyoto. On June 23, 2026, NTT WEST announced two new data centers: Osaka Minami (Chuo-ku, Osaka; 8 MW IT load; completion planned for FY2031) and Hakata (Hakata-ku, Fukuoka; 5 MW IT load; completion planned for FY2029)
NTT says liquid cooling can cut the power used for cooling by up to 60% compared with air cooling.

Photo 1: Server racks in a data center (illustrative only; taken in 2011 at a research facility in the United States and unrelated to the facilities in this report. Photo: Derrick Coetzee, CC0, Wikimedia Commons, cropped and resized)
NTT has not disclosed an investment amount. On August 4, 2026, Bloomberg reported, citing people familiar with the matter, that NTT DATA expects to spend at least ¥1.5 trillion (about US$9.6 billion, excluding AI accelerators) through 2033 to expand to about 1 GW. According to the same report, an NTT DATA spokesperson said the company does not disclose investment plans.
3. Large Regional Projects: Akita, Kagoshima and Hokkaido
On September 11, 2026, the Ministry of Economy, Trade and Industry (METI) certified the first round of "GX Strategic Areas". The data-center-cluster type aims to form GW-scale data center clusters over roughly the next 10 years and covers 9 regions at 10 sites: Hokkaido (Ishikari, Tomakomai), Akita (Akita City), Miyagi (Tomiya), Tochigi (Yaita), Ibaraki (Joso/Tsukuba), Toyama (Nanto), Kagawa (Ayagawa/Sakaide/Marugame), Fukuoka (Kitakyushu/Nogata/Kurate) and Kagoshima (Satsumasendai). The certifications carry conditions such as steady progress of the plans and securing coexistence with local communities.

Figure 1: Large AI data center plans in Japan (power-receiving capacity at full planned scale, as of October 28, 2026. Created by Two Sheep from company and local government announcements and news reports. KDDI's Osaka Sakai Data Center, which is operating, is not included because its power-receiving capacity has not been disclosed; NTT's roughly 1 GW is not included because it is IT power capacity)
Northern Akita City
On October 27, 2025, Akita City announced a partnership agreement with Bitgrit, inc. and S2 Co., Ltd. The agreement centers on siting an AI data center powered by renewable energy and on training and hiring data scientists. On August 6, 2026, Kyodo News reported, citing Akita Prefecture and S2, that an industrial park in northern Akita City is the candidate site, with up to 500 MW of power-receiving capacity assumed, development costs expected to reach about ¥2 trillion, and operation targeted for the early 2030s. According to the same report, Mubadala Investment Company, a government-backed fund of the United Arab Emirates (UAE), is considering investing.
Satsumasendai, Kagoshima Prefecture
At Circular Park Kyushu, on the site of Kyushu Electric Power's former Sendai thermal power station, Kai Shin Digital Infrastructure (凱信数基), set up under the lead of Taiwan's CDIB Capital Group, is planning an AI data center. The company was established on January 20, 2026 and signed a siting agreement with Satsumasendai City on July 18. According to the city, the plan starts with demonstration operation and expands in phases to an AI data center of 350 MW cumulative, with planned investment of about ¥850 billion (at the 350 MW stage, subject to change). Separately, the city expects about ¥2 trillion of AI data center server-related investment across the whole Circular Park Kyushu site. Kyodo News reported that construction is to start within FY2026, small-scale operation is to begin from FY2027 alongside construction, and full operation is targeted by FY2032.
Hokkaido (Ishikari and Tomakomai)
SoftBank is building an AI data center on a site of about 70 hectares in Tomakomai, Hokkaido. It will first open at about 50 MW, its power-receiving capacity is expected to grow to more than 300 MW, and it is targeting an opening within FY2026 (as of October 21, 2026). In Ishikari, the Ishikari Renewable Energy Data Center No.1, with 15 MW of power-receiving capacity, was completed on March 27, 2026 and began service for its data halls on August 1.
On October 20, 2026, Hokkaido, together with Ishikari and Tomakomai cities, opened a public call for data center operators to take over grid-connection applications the prefecture had already filed. Ishikari offers five grid applications totaling 590 MW (indicative connection from October 2031 to December 2032 or later, depending on the application), and Tomakomai offers 400 MW on a site of about 47 hectares (indicative connection from August 2030 or later).
4. Reusing a Factory Site: AI Data Centers in Sakai
On the former Sharp Sakai plant site in Sakai, Osaka Prefecture, KDDI already operates an AI data center and SoftBank is building one.

Photo 2: Sakai-Senboku Coastal Industrial Zone (illustrative only; it does not show the facilities in this report. Photo: Sakai Yayoi, CC0, Wikimedia Commons, resized)
KDDI acquired land and buildings at Sharp's Sakai plant in April 2025 and built the Osaka Sakai Data Center in about six months by reusing the plant's large-scale power and cooling equipment. The data center began operating on January 22, 2026 and runs AI servers including NVIDIA GB200 NVL72 using direct liquid cooling in addition to conventional air cooling. The building has four floors above ground and a total floor area of about 57,000 m², and it uses 100% renewable-derived electricity. Its power-receiving capacity has not been disclosed. KDDI GPU Cloud, the GPU cloud service offered from the facility, has been accepting applications since April 1, 2026. On October 27, 2026, KDDI announced it will add AI models to the facility's inference environment step by step from December 2026 and plans to introduce NVIDIA HGX Rubin NVL8 in FY2027.
On March 14, 2025, SoftBank signed a contract to acquire land (about 450,000 m²) and buildings (about 840,000 m² of total floor area) related to Sharp's LCD panel plant in Sakai for about ¥100 billion. At the time, it aimed to start operation within 2026 with about 150 MW of power-receiving capacity, expanding to more than 250 MW in the future. On May 11, 2026, Nikkei reported that SoftBank's new mid-term plan puts the start of operation of the large Sakai data center in FY2027. On the same day, SoftBank announced plans to build an "AX Factory" and a "GX Factory" on the same site, centered on the Sakai AI data center, and to start manufacturing battery cells and energy storage systems in FY2027.
5. The Government's Investment Plans
On July 21, 2026, the Cabinet approved Japan's Growth Strategy. On the same day, the Japan Growth Strategy Headquarters decided the Public-Private Investment Roadmap for Key Products and Technologies in 17 Strategic Fields. Public and private investment, mainly in Japan, across the 62 key products and technologies is projected at over ¥370 trillion cumulatively by FY2040, excluding overlaps.
For the "cloud and data centers, and batteries" item (part of the digital and cybersecurity field), the roadmap assumes ¥32.7 trillion of public and private investment through FY2035, with an economic ripple effect of ¥107.1 trillion. The ¥32.7 trillion covers cloud, data centers and batteries together; no separate figure is given for data centers. The roadmap describes the domestic cloud market as currently worth about ¥4 trillion and growing by more than 20% a year; Japan's Growth Strategy aims to grow it to ¥30 trillion by 2035 and to triple battery-related sales by 2035.
At the Japan Growth Strategy Council on October 1, 2026, the government said it will compile a Japan Growth Strategy Implementation Plan by the end of the year, setting out the content and amount of domestic investment over roughly the next five years. In a policy speech on October 5, Prime Minister Takaichi said the government will secure a sufficient and stable power supply that can also meet rising data center electricity demand as AI is put to use across society.
6. Power: Demand Outlook and Grid Connection
In its demand forecast published on January 21, 2026, the Organization for Cross-regional Coordination of Transmission Operators (OCCTO) counts separately, within national peak demand, 0.83 GW in FY2026, 4.20 GW in FY2030 and 7.62 GW in FY2035 for new and expanded data centers and semiconductor plants. Of these, data centers account for 0.64 GW, 3.28 GW and 6.61 GW.

Figure 2: Forecast peak demand from new and expanded data centers (national total, sending-end. Source: OCCTO, demand forecast for Japan and each supply area, FY2026. Created by Two Sheep)
According to OCCTO, reflecting operators' revisions of their build plans and the record of existing data centers, the data center figure runs below the previous forecast through FY2033 and above it from FY2034. OCCTO also notes that, mainly at data centers, plan changes from construction postponements, delays and design changes are pushing start-up dates later.
In the Tokyo area, TEPCO Power Grid had received cumulative wheeling applications from data centers of about 17.9 GW (including expected contracts) as of the end of March 2026. This is the total of applications already received (contract power), not current demand. TEPCO Power Grid's materials show supply to data centers rising from 0.64 GW in 2025 to 4.48 GW in 2030 and about 17.9 GW in 2037 or later. In the Inzai area of Chiba Prefecture, where many data centers are located, the Chiba Inzai substation (275/66 kV) began operating on June 5, 2024. To meet demand from new data centers, TEPCO Power Grid also plans further reinforcement work, including new substations.

Photo 3: The 500 kV Fukushima Trunk Line in Daigo, Ibaraki Prefecture (illustrative only; taken in 2019 and unrelated to the projects in this report. Photo: Σ64, CC BY 4.0, Wikimedia Commons, resized)
According to the 2026 White Paper on Information and Communications from the Ministry of Internal Affairs and Communications (MIC), about 90% of Japan's data centers are concentrated in the Tokyo and Osaka areas. MIC and METI set up the Watt-Bit Public-Private Council in March 2025, and its June 2025 summary called for building several new data center clusters, each GW-scale, in addition to existing clusters. "Watt-Bit collaboration", which develops power and communications infrastructure together, is also part of Japan's second AI Basic Plan, approved by the Cabinet on July 14, 2026.
7. What Two Sheep Co., Ltd. Provides
Headquartered in the Telecom Center Building in Aomi, Koto-ku, Tokyo, Two Sheep Co., Ltd. provides on-site work in data centers and shipping and deployment services for IT equipment.
- 24/7/365 Remote Hands: in data centers in Tokyo and Osaka, we handle server racking, cabling, replacement of failed parts (RMA) and status checks.
- International shipping and customs clearance for IT equipment: we arrange equipment procured overseas all the way into the data center.
- Migrations, connectivity and optical modules: we handle data center migrations, arrange IP Transit and leased lines, and sell optical modules (ModuleSheep).
- Japanese, English and Chinese: we coordinate between overseas customers and data centers in Japan.
Our track record includes moving 100 production servers from Equinix TY8 to AT TOKYO CC1 within a planned maintenance window.
Related Videos
- ▶ KDDI (official): 【KDDI NEWS】大阪堺データセンター (Osaka Sakai Data Center; January 2026, YouTube, 0:37)
- ▶ NTT (official): Power and ICT resource control for Watt-Bit collaboration (Japanese; February 2026, YouTube, 3:49)
Main Sources
- Nikkei: report on NTT and an Anthropic data center (October 13, 2026, Japanese)
- Nikkei Asia: report on NTT and an Anthropic data center
- Reuters: relaying the Nikkei report (The Star)
- NTT: AIOWN AI-native infrastructure and domestic data center plans (April 27, 2026, Japanese)
- Bloomberg: report on NTT DATA's investment (Energy Connects, August 4, 2026)
- NTT DATA: opening of the Keihanna OSK11 Data Center (April 9, 2026, Japanese)
- NTT WEST: new Osaka Minami and Hakata data centers (June 23, 2026, Japanese)
- Microsoft: US$10 billion investment in Japan (April 3, 2026)
- AWS: investment plan for cloud infrastructure in Japan (January 19, 2024)
- Oracle: plan to invest more than US$8 billion in Japan (PR Newswire, April 18, 2024)
- METI: certification of the first round of GX Strategic Areas (September 11, 2026, Japanese)
- Akita City: partnership agreement with Bitgrit, inc. and S2 Co., Ltd. (October 27, 2025, Japanese)
- Kyodo News: Akita data center plan (Kumamoto Nichinichi Shimbun, August 6, 2026, Japanese)
- Satsumasendai City: siting agreement with Kai Shin Digital Infrastructure (July 18, 2026, Japanese)
- Kyodo News: Kagoshima data center plan (Kumamoto Nichinichi Shimbun, July 18, 2026, Japanese)
- SoftBank: Hokkaido Tomakomai AI Data Center (October 21, 2026, Japanese)
- Hokkaido: public call to take over grid applications (October 20, 2026, Japanese)
- KDDI: Osaka Sakai Data Center begins operation (January 22, 2026, Japanese)
- KDDI: expanded inference environment at the Osaka Sakai Data Center (October 27, 2026, Japanese)
- SoftBank: acquisition of land and buildings at Sharp's Sakai plant (March 14, 2025, Japanese)
- SoftBank: launch of a domestic battery business (May 11, 2026, Japanese)
- Cabinet Secretariat: Japan's Growth Strategy (Japanese)
- Cabinet Secretariat: Public-Private Investment Roadmap (Japanese)
- Cabinet Secretariat: Public-Private Investment Roadmap, reference material (Japanese)
- Prime Minister's Office: policy speech to the 222nd Diet session (October 5, 2026, Japanese)
- OCCTO: FY2026 demand forecast (January 21, 2026, Japanese)
- TEPCO Power Grid: current status and outlook (August 2026, Japanese)
- MIC: 2026 White Paper on Information and Communications, regional dispersal of data centers (Japanese)
- MIC: Watt-Bit Public-Private Council Summary 1.0 (June 12, 2025, Japanese)
About This Report
- This report was compiled independently by Two Sheep Co., Ltd. from public information such as company and local government press releases, government documents and news reports (as of October 28, 2026). Items based only on news reports are marked as such. Company plans may change. This report is for information only and is not a recommendation of any particular company or investment.
- Companies are named only to describe industry trends; this does not indicate any business relationship with us. Company, product and facility names mentioned are trademarks or registered trademarks of their respective owners.